A.D. Harvey Production Expansion Project | ARTi Ltd

Written by Advanced Resin | Jan 2, 2021 10:30:00 AM

Location: Norwich

Project Size: Approx 400sqm2

Project Specification: Polyurethane screed

  • Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding
  • Cut all perimeter anchor points and transitions
  • Apply DPM primer and Blind with quartz aggregates
  • Apply 9mm polyurethane screed in chosen Ral
  • Apply Polyurethane wall render to all 0.5 metre-high concrete kerbs
  • Apply polyurethane jointing compound to all joints and transitions
  • The project was completed in 5 days