Removing Surface Contamination & Applying Epoxy Primer Before Applying Polyurethane Screed For Food Manufacturing Facility In 3 Days

By Advanced Resin on Jun 9, 2026 2:37:31 PM

food-manufacturing-facility

 

locations: Stoke

overall size of the project: 300

specification: Polyurethane Screed

  • Prepare substrate via vacuum-enclosed diamond grinding to remove all surface contamination and leave a smooth mechanical finish.
  • Apply Epoxy Primer coat and blind with quartz aggregate
  • Apply 9mm Polyurethane screed in chosen Ral colour.
  • Apply Coved skirting to perimeter areas and bring through expansion joints.
  • Project completed in 3 days

 