Blog - Advanced Resin Technologies International Ltd

Case Study | Fixing Imperfections & Applying Durable Epoxy Coatings

Written by Advanced Resin | Jun 8, 2026 3:55:30 PM

 

locations: Nottingham UK

overall size of the project: approx. 175M2

system: epoxy coating system

  • Goods in/out
  • Prepared by captive shot blasting and 3 phased planetary grinders.
  • Apply 1st epoxy dpm primer and allow to cure.
  • Fill all minor imperfections or holes and apply 2nd epoxy primer.
  • Apply 1st coat of epoxy coating.
  • Apply 2nd and final coat of epoxy high-build coating.
  • Completed in 3 days