Blog - Advanced Resin Technologies International Ltd

Case Study | Durable Polyurethane Screed For IPL LTD’s Forktuck Turning Side

Written by Advanced Resin | Jun 9, 2026, 11:18:08 AM

 


locations:
Telford

overall size of the project: Approx 90sqm2

specification: Polyurethane screed

  • Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding.
  • Cut all perimeter anchor points and transitions.
  • Prime all areas with Epoxy DPM primer and blind with quartz aggregates.
  • Apply 6mm polyurethane screed in chosen Ral.
  • The project was completed in 2 days.