Removing Failed Flooring & Applying Our Durable Protective Polyurethan Screed In Chosen RAL In Just 2 Days For IPL LTD’s Forktuck Turning Isle

By Advanced Resin on Jun 9, 2026 12:18:08 PM

ipl-itd-forktuck-turning-side

 


locations:
Telford

overall size of the project: Approx 90sqm2

specification: Polyurethane screed

  • Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding.
  • Cut all perimeter anchor points and transitions.
  • Prime all areas with Epoxy DPM primer and blind with quartz aggregates.
  • Apply 6mm polyurethane screed in chosen Ral.
  • The project was completed in 2 days.

 

 