Repairing & Replacing Failed Coating In MOT Station Stoke With Our Trusted And Durable Epoxy Flake System & UV Stable Polyaspartic Demarcations For Safety
By Advanced Resin on Jun 9, 2026 10:35:27 AM
.webp)
locations: Stoke
overall size of the project: Approx 250sqm2
system: Epoxy Flake System
- Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding.
- Repair all surface defects with epoxy repair mortar and prime with Epoxy DPM coatings.
- Apply a Base coat of Epoxy and blind with Decorative PVA Flakes.
- Apply 2 coats of UV-stable epoxy coating
- Apply all Demarcations in UV stable Polyaspartic Coatings
- The project was completed in 5 days.
- case studies (79)
- News (39)
- Epoxy Flooring (33)
- Commercial Resin Flooring (31)
- Industrial Resin Flooring (19)
- Commerical flooring (13)
- Resin Driveways (10)
- industrial flooring (9)
- Polyurethane (8)
- Food Industry (6)
- Polyurethane Flooring (6)
- Polyurethane Screeds (5)
- MMA Flooring (4)
- Commercial Flooring (3)
- Industrial (3)
- Interior (2)
- Resin Flooring (2)
- Anti-Static Flooring (1)
- Anti-slip (1)
- Car Park Flooring (1)
- Gym Changing Rooms (1)
- Retail flooring (1)
- Screed (1)
- Underfloor Heating (1)
- Work (1)
- resin bonded driveway (1)
- resin bound driveway (1)
- June 2026 (67)
- May 2026 (3)
- April 2026 (2)
- March 2026 (2)
- January 2026 (1)
- December 2025 (2)
- November 2025 (2)
- October 2025 (2)
- September 2025 (2)
- July 2025 (3)
- June 2025 (3)
- May 2025 (4)
- April 2025 (4)
- March 2025 (1)
- February 2025 (2)
- November 2024 (2)
- October 2024 (1)
- September 2024 (2)
- August 2024 (2)
- July 2024 (2)
- June 2024 (2)
- May 2024 (2)
- April 2024 (2)
- March 2024 (2)
- February 2024 (2)
- January 2024 (2)
- December 2023 (2)
- November 2023 (2)
- October 2023 (2)
- September 2023 (2)
- August 2023 (2)
- July 2023 (2)
- June 2023 (2)
- May 2023 (2)
- January 2021 (1)
- December 2020 (7)
- November 2020 (1)
- August 2020 (2)
- June 2020 (1)
- May 2020 (1)
- March 2020 (1)
Subscribe by email
Share this
You May Also Like
These Related Stories
Removing Surface Contamination & Fixing Cracks Before Applying Durable Epoxy Coatings In Chosen RAL Colours For An Engineering Workshop In 2 Days

Removing Surface Contamination & Fixing Cracks Before Applying Durable Epoxy Coatings In Chosen RAL Colours For An Engineering Workshop In 2 Days
Jun 9, 2026 2:17:06 PM
1
min read
Completing High-Quality & Durable Polyurethane Screed For 4,000m2 Cargill Foods Chicken Processing Plant

Completing High-Quality & Durable Polyurethane Screed For 4,000m2 Cargill Foods Chicken Processing Plant
Jun 9, 2026 2:08:32 PM
1
min read
Grinding Substrate To Remove Existing Failed Flooring & Replacing It With Durable Polyurethane Screed For Bulk Powder Wash Down Room In 4 Days

Grinding Substrate To Remove Existing Failed Flooring & Replacing It With Durable Polyurethane Screed For Bulk Powder Wash Down Room In 4 Days
Jun 9, 2026 1:16:31 PM
1
min read



No Comments Yet
Let us know what you think