Removing Surface Contamination In Bacon & Sausage Factory And Applying Highly Durable Polyurethane Screed & Jointing Materials in 7 Days

By Advanced Resin on Jun 9, 2026 3:01:35 PM

bacon-sausage-factory

 

Location: Reading

Project Size: Approx 400m2

Project Specification: Polyurethane screed

  • prepare substrate via vacuum-enclosed diamond grinding to remove all surface contamination and leave a clean textured mechanical finish
  • Apply Moisture Tolerant Primer to the entire area and blind with quartz aggregates
  • Cut all perimeter anchor points
  • Apply nominal 9mm polyurethane screed to all areas
  • Apply polyurethane coving render to all wall details
  • Apply polyurethane jointing materials to all movement joints and drain details
  • Project complete in 7 days

 